Holy Name Center New Facility

Barry Forbes President

Barry Forbes, President, says:

build a legacy of hope

“With $60 million fully funded — including $10 million dedicated to land acquisition, $45 million allocated to development and construction, and three years of operating expenses — Holy Name Center will emerge as a safe, compassionate community where mothers and children can find stability, support, and a path toward independence.”

Safe facilities for mothers and children

The center will offer housing for up to 50 pregnant women, some with one or two small children, etc., with plans for an optional future wing that could expand capacity to serve an additional 50 women and children.

Safe Housing & Expansion

Residents will also have access to counseling, mentoring, and faith-based support, as well as early childhood support and developmental resources designed to promote healthy growth and long-term well-being for their children.

the center will include

  • Studio and two-room apartments

  • A commercial kitchen and eating area

  • Counseling offices

  • Early childhood rooms & outdoor play yard

  • Chapel & quiet reflection spaces

  • Education and job-readiness classrooms

  • A high-security environment

Full dining and care facilities are provided

In addition to shelter and every day needs, Holy Name Center will provide prenatal and emotional support, parenting and infant care education, and life-skills training to help mothers build stable futures for themselves and their families.

the timeline

Phase 1
Phase 1

Vision & feasibility

Duration: 6 months

Completion: 12/2026

Phase 2
Phase 2

Zoning/Entitlements

Duration: 4-12 months

Completion: 06/2028

Phase 3
Phase 3

Fundraising Prep

Duration: 4-8 months

Completion: 10/2027

Phase 4
Phase 4

Schematic Design

Duration: 2-4 months

Completion: 12/2027

Phase 5
Phase 5

Land Acquisition

Duration: 3-12 months

Completion: 03/2028

Phase 6
Phase 6

Construction Documents

Duration: 4-8 months

Completion: 12/2028

Phase 7
Phase 7

Financing/Fundraising Completion

Duration: Ongoing

Completion: 02/2029

Phase 8
Phase 8

Permitting/Bidding

Duration: 2-5 months

Completion: 04/2029

Phase 9
Phase 9

Site Work

Duration: 2-4 months

Completion: 09/2029

Phase 10
Phase 10

Vertical Construction

Duration: 10-18 months

Completion: 10/2029

Phase 11
Phase 11

Furnishing/Operations

Duration: 2-4 months

Completion: 10/2030

Phase 12
Phase 12

Final Inspection/Move-In

Duration: 1-2 months

Completion: 02/2031